Enbridge Can Begin Bayway Lateral Construction

Posted on

FERC has approved Enbridge’s request to commence construction of the Bayway Lateral Project in Union County, New Jersey.

The Bayway Lateral Project, which will will interconnect with Enbridge’s New Jersey – New York Expansion Project and transport 300,000 dekatherms of natural gas per day, includes the installation of approximately 2,300 linear feet of 24-inch-diameter pipeline connecting the company’s existing Line 38 to the Linden Cogen Power Plant and Phillips 66 Bayway Refinery, along with construction of one new fenced metering and regulating station on the Phillips 66-owned property adjacent to the Linden Cogen Power Plant.

The project is expected to be completed in Jan. 2018.