FERC Approves Another Hillabee Expansion Request

Posted on

FERC has approved Williams’ request to modify the crossing of a pond in Tallapoosa County, Alabama as part of the Hillabee Expansion Project.

Earlier this month, FERC OK’d the following requests for the project:

  • To relocate the mainline tie-in facility and alter access roads AR- CS84-4 and AR-Logging Road at Compressor Station 84 in Choctaw County, Alabama
  • To utilize additional temporary workspace, create a new permanent access road, and convert a previously approved permanent access road to a temporary access road in Tallapoosa County, Alabama

The Hillabee Expansion Project will expand the existing Transco pipeline’s capacity in Alabama and transport gas to the proposed Sabal Trail pipeline. The project is to be built in three phases, with the first phase expected to be finished in the second quarter of 2017. Once done, the pipeline will add a total of approximately 1,131,000 dekatherms per day of pipeline capacity to the Transco system by 2021.