FERC Approves More Rover Pipeline Construction

Posted on

FERC has approved Energy Transfer Partners’ request to commence construction of the Rover Pipeline facilities in the following areas:

  •   cultural resources site numbers 33ST1088 and 33WE662 and the associated 500-foot buffers
  •   the Pinckney State Recreation Area

The Rover Pipeline Project includes new interstate pipeline and related facilities extending from the Appalachian supply area to a proposed interconnection with Vector Pipeline, LP in Livingston County, Michigan. The Rover Pipeline will transport up to 3.25 billion cubic feet per day of domestically-produced natural gas to markets in the Midwest, Northeast, East Coast, Gulf Coast and Canada, with direct deliveries to Ohio, West Virginia, Michigan, and into the Dawn Hub in Ontario, Canada, which has a broader network of distribution points back into the U.S.

The project is expected to be completed in November 2017.