National Fuel Kicks off Construction Projects

June 2017

FERC has approved National Fuel Gas Supply Corp.’s request to proceed with construction of Line T2KNY, Line KNY abandonment, and associated modifications at East Eden and North Boston Meter and Regulator Stations in Erie County, NY for the Line T2KNY Install, Line TNY Replacement, and Line KNY Abandonment Project.

The Line T2KNY Install, Line TNY Replacement, and Line KNY Abandonment Project consists of installing approximately 1.2 miles of new 20-inch natural gas pipeline (Line T2KNY), replacing approximately 6.7 miles of 20-inch bare steel pipeline with 7.0 miles of 24-inch coated natural gas pipeline (Line TNY), the abandonment of approximately 14.9 miles of 20-inch bare steel natural gas pipeline (Line KNY), modifications at the North Boston and East Eden meter and regulator stations and the Zoar Compressor Station in Erie County, NY.

Once completed, the project will provide an additional 2.6 MDth/d of new firm capacity.