FERC OK’s More Atlantic Sunrise Construction

Posted on

FERC has approved the following Williams’ requests in Pennsylvania for the Atlantic Sunrise pipeline project:

  • To construct the Central Penn Line North Pipeline
  • To construct the Central Penn Line South Pipeline
  • To construct Meter and Regulatory Stations,
  • To use contractor yards, including the new High Ridge Contractor Yard in Schuylkill County, Pa.

The Atlantic Sunrise pipeline project includes the following:

  • Approximately 183 miles of new greenfield pipe (Central Penn North & Central Penn South)
  • Two pipeline loops totaling about 12 miles (Chapman Loop, Unity Loop)
    Two and half miles of existing pipeline replacement
  • Two new compressor facilities in Pennsylvania
  • Other facility additions or modifications in Pennsylvania, Maryland, Virginia, North Carolina, and South Carolina

Once finished, the project will add 1.7 million Dth/d of pipeline capacity to Williams’ Transco system, and is expected to be placed in service in 2018.

 