FERC OKs Multiple Hillabee Expansion Requests

Posted on

FERC has approved the following requests as part of Williams’ Hillabee Expansion Project:

  • The use of 0.15 acre of additional temporary workspace at milepost 887.0 of the Billingsley Loop in Autauga County, Alabama.
  • The use of an existing 25-foot-wide, 902-foot long temporary access road near milepost 886.8 in Autauga County, Alabama.
  • The use of an existing 25-foot-wide, 520-foot long temporary access road near milepost 887.0 in Autauga County, Alabama.

Once completed, the Hillabee Expansion Project will increase the existing Transco pipeline’s capacity in Alabama and deliver gas to the proposed Sabal Trail pipeline. The project will be constructed in three phases, with the first phase expected to be finished in the second quarter of 2017. The pipeline will add a total of approximately 1,131,000 dekatherms per day of pipeline capacity to the Transco system by 2021.