FERC has approved National Fuel Gas Supply Corporation’s request to proceed with construction of Line TNY and associated modifications at the Zoar Compressor Station in Erie County, New York for the Line T2KNY Install, Line TNY Replacement, and Line KNY Abandonment Project.

The Line T2KNY Install, Line TNY Replacement, and Line KNY Abandonment Project includes the installation of approximately 1.2 miles of new 20-inch natural gas pipeline (Line T2KNY), replacing approximately 6.7 miles of 20-inch bare steel pipeline with 7.0 miles of 24-inch coated natural gas pipeline (Line TNY), the abandonment of approximately 14.9 miles of 20-inch bare steel natural gas pipeline (Line KNY), and modifications at the North Boston and East Eden meter and regulator stations and the Zoar Compressor Station in Erie County, NY.

Once finished, the project will provide an additional 2.6 MDth/d of new firm capacity.